Metso Insights Case studies Mining and metals refining Turn-key flotation retrofit with fast turnaround for Yamana Gold in Brazil
Mining Metals refining
Jan 3, 2017

Turn-key flotation retrofit with fast turnaround for Yamana Gold in Brazil

Outotec delivered an extremely fast turnaround, minimizing production losses and increasing recovery while improving the availability and energy efficiency of the flotation cells.

Yamana Gold is a Canadian-based gold producer, with mines and operations in Canada, Mexico, Brazil, Argentina, and Chile. The Chapada open pit gold-copper mine in Brazil began production in 2007. It is a relatively low-cost operation and contributes significantly to Yamana’s favorable cost structure. 

Last year, Metso Outotec delivered a new Courier on-stream analyzer, which enabled Yamana operators to detect that they were losing a significant amount of valuables to tailings. In addition, the flotation circuit suffered from poor availability that was caused by the heavy sanding of the other supplier´s flotation cells. Yamana was also looking for a partner to continuously improve their operations. These factors contributed to Yamana seeking ways to further improve its flotation circuit performance.

In mid-2015 Daniel Diez, responsible for Yamana Gold business and operations development in South Americas, and the entire site processing team were seeking ways to improve the flotation circuit performance at their Chapada gold-copper mine in Brazil.

After thorough research of available technological options, including the FloatForce value calculator at www.outotec.com to estimate the potential return of investment (ROI) of a flotation retrofit project, Outotec´s experts were contacted to jointly develop a solution to solve Yamana´s operation challenges in Chapada flotation circuit.

In March 2016, Metso Outotec began turn-key retrofit of 10 existing 160m³ non-Outotec flotation cells with Outotec TankCell® and FloatForce® technology.

Check the video
00:00
Watch video of turn-key flotation retrofit in Brazil

Project Scope

The project scope included Computational Fluid Dynamics (CFD) studies, basic and detailed engineering, shutdown planning, delivery of proprietary equipment, turn-key installation, commissioningassisted operation, and advanced on-site personnel training. Outotec´s manufacturing and service workshop in Guarapari, Brazil, gave additional benefits and flexibility to this project.

At the beginning of the project, Metso Outotec completed an in-depth metallurgical assessment of the rougher/ scavenger flotation circuit and identified a large potential for improvement in the flotation plant, which could positively impact the overall copper and gold recoveries. An on-site mechanical assessment with advanced laser 3D scanning was implemented by Outotec in co-operation with Yamana to find out all required technical details for the installation and shutdown planning.

Metso Outotec offered a turn-key project delivery, manufacturing custom made steelworks in Brazil and importing only specialist items, took care of logistics, disassembly and removal of old equipment, installation and mechanical completion of new cells, implemented all commissioning phases, started up the flotation cells in cooperation with Yamana personnel with slurry. Process testing was done in cooperation with Yamana process experts. All installation and commissioning personnel were provided by Outotec (except for certain electrical specialists which were contracted locally). In total, more than 80 Outotec representatives implemented the modernization during day and night shifts.

In addition to retrofit and turn-key delivery, advanced operator training with our Virtual Experience training was provided by Metso Outotec.

Outotec developed a concept with the target to minimize the shutdown period, which takes the total cost of the project and the return of investment into consideration.
Outotec developed a concept with the target to minimize the shutdown period, which takes the total cost of the project and the return of investment into consideration.

Fast and efficient shutdown

The shutdown took place in two phases, one line of five flotation cells at a time. This meant that the process was able to continue with half the equipment operational at all times.

“As the reduction of production loss due to the installation work was of utmost importance to the customer, Outotec developed a concept with the target to minimize the shutdown period, which takes the total cost of the project and the return of investment into consideration. With this concept and the full solution including demolition, installation and commissioning and shutdown process know-how, Outotec offered the added value to the customer and won the project,” said André Batista, Sales Director, Outotec Brazil.

Cooperation continues by debottlenecking other parts of the process to ensure peak performance of the whole plant.

*This case study has been written prior to the merger of Metso and Outotec.

How much could you be saving?
Try out our online value calculator to see what economic and environmental benefits the FloatForce upgrade can bring to your operations.
Enjoyed this article? Try this next
Flotation upgrade at Nui Phao
Outotec FloatForce mechanism and SkimAir float cell deliver better mechanism wear life at Masan Resources in Vietnam.
Read more
Mining Metals refining

Contact our sales to achieve similar results

Select your industry to open the form.
Mining
Metals refining
Your information is safe. Check our privacy notice for more details.
Thank you!
We will shortly contact you. You can send a new inquiry again after 15 minutes.